Four two-carriageway bridges (11.80 m), of two beams of between 28-49 m long and between 4-18 isostatic spans, with piles executed “in situ”.
To be highlighted:
Work | Toll-less motorway A-21, section Jaca (Oeste) - Santa Cilia de Jaca (Huesca) |
---|---|
Building company | FCC |
Administration | Directorate General of Roads, Ministry of Development |
Products | 7,000 m2 of U-beams, 31,000 m2 of reinforced floor slab with lattice for cantilever and 7,800 m2 of prestressed floor slab. |